Grand Chute, Wisconsin
Grand Chute, Wisconsin

Capitol Dr Redundant Water Main

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$825,000

Overview

DepartmentSanitary District 1 - Water
Project NumberPWS1-28-001
TypeImprovement
CategoryWater
Priority2 Very Important
StatusActive
Useful Life75 years years
Paser Rating:NA
Project Length (mi.):NA
Budget Items20292030Total
Water - Sanitary District No. 175,0000825,000
Total75,0000825,000

Project Description

Install redundant 16-inch water main pipes along Capitol Drive between STH 47 and Story Street.

Project Justification

Needed to maintain system performance and provide service to the eastern portion of town.

Spend

Expenditures20292030Total
Construction0750,000750,000
Engineering75,000075,000
Total75,000750,000825,000
Funding Sources20292030Total
San 1 Debt75,0000825,000
Total75,0000825,000