Carter Woods Park Shelter Upgrade Allowance

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$112,000

Overview

DepartmentParks and Recreation
Project NumberPR-28-015
TypeImprovement
CategoryPark Improvements
Priority3 Important
StatusActive
Useful Life20 years years
Paser Rating:N/A
Project Length (mi.):N/A
Budget Items2030Total
Park Improvement12,00012,000
Total12,00012,000

Project Description

Complete remodel of restrooms and kitchen area, including plumbing and electrical needs.

Project Justification

The restrooms and kitchen area are currently in need of updating. These items have only been slightly updated since the development of the shelter in 1975.

Spend

Expenditures2030TotalFuture
Engineering12,00012,000100,000
Total12,00012,000
Funding Sources2030TotalFuture
General Obligation Debt 203012,00012,000100,000
Total12,00012,000