Capital Cost
TOTAL PROJECT COST$58,000
Overview
DepartmentParks and Recreation
Project NumberPR-28-005
TypeUnassigned
CategoryPark Improvements
Priority3 Important
StatusActive
Useful Life20 years years
| Budget Items | 2026 | Total | ||
|---|---|---|---|---|
| Capital Equipment - Parks | 58,000 | 58,000 | ||
| Total | 58,000 | 58,000 |
Project Description
Upgrading the existing high-pressure sodium lighting to LED in the park.
Project Justification
Converting existing lighting to LED’s would make them more energy efficient, reduce operating costs, and allow for better play conditions on the pickelball courts and ball fields in the park.
Spend
| Expenditures | 2026 | Total | ||
|---|---|---|---|---|
| Construction | 58,000 | 58,000 | ||
| Total | 58,000 | 58,000 |
| Funding Sources | 2026 | Total | ||
|---|---|---|---|---|
| General Obligation Debt 2026 | 58,000 | 58,000 | ||
| Total | 58,000 | 58,000 |