Capital Cost
TOTAL PROJECT COST$120,000
Overview
DepartmentStreets
Project NumberPWSTR-25-040
TypeImprovement
CategoryReconstruction
Priority3 Important
StatusActive
Useful Life20 years years
Paser Rating:NA
Project Length (mi.):NA
| Budget Items | 2026 | Total | ||
|---|---|---|---|---|
| Street Other | 120,000 | 120,000 | ||
| Total | 120,000 | 120,000 |
Project Description
Community Sensitive Design features (including landscaping) will be installed within the new DDI at I-41/STH 15 when the interchange is reconstructed in 2025 by WisDOT. Also includes costs for the same work within the new DDI at STH 47 (Richmond) when the interchange is reconstructed in 2026 by WisDOT. Costs also include staining of the concrete bridges and retaining walls within the I-41 corridor.
Project Justification
Any costs for community sensitive design features (other than concrete or grass) is passed onto the locals to fund/pay.
Spend
| Expenditures | 2026 | Total | ||
|---|---|---|---|---|
| Construction | 120,000 | 120,000 | ||
| Total | 120,000 | 120,000 |
| Funding Sources | 2026 | Total | ||
|---|---|---|---|---|
| General Obligation Debt 2026 | 120,000 | 120,000 | ||
| Total | 120,000 | 120,000 |