Capital Cost
TOTAL PROJECT COST$75,000
Overview
DepartmentStreets
Project NumberPWSTR-27-001
TypeImprovement
CategoryUrbanization
Priorityn/a
StatusActive
Useful Life20 years years
Paser Rating:5-7
Project Length (mi.):0.92
| Budget Items | 2027 | Total | ||
|---|---|---|---|---|
| Engineering Streets | 75,000 | 75,000 | ||
| Total | 75,000 | 75,000 |
Project Description
County led urbanization project. Assume 50% cost share with Grand Chute and Fox Crossing.
Project Justification
Within Bike/Ped plan for mutli-use trail.
Spend
| Expenditures | 2027 | Total | ||
|---|---|---|---|---|
| Engineering | 75,000 | 75,000 | ||
| Total | 75,000 | 75,000 |
| Funding Sources | 2027 | Total | ||
|---|---|---|---|---|
| General Obligation Debt 2028 | 75,000 | 75,000 | ||
| Total | 75,000 | 75,000 |