Capital Cost
TOTAL PROJECT COST$825,000
Overview
- Department
- Sanitary District 2 - Sewer
- Project Number
- PWS2-26-004
- Type
- Improvement
- Category
- Wastewater
- Priority
- 3 Important
- Status
- Active
- Useful Life
- 75 years years
- Paser Rating:
- NA
- Project Length (mi.):
- NA
| Budget Items | 2028 | 2029 | Total |
|---|---|---|---|
| Sewer - Sanitary District No. 2 | 75,000 | 750,000 | 825,000 |
| Total | 75,000 | 750,000 | 825,000 |
Project Description
Design of new lift station in the southeast corner of the intersection of CTH JJ and N. Indigo Lane to accommodate sewer extension along CTH JJ and future development to the north.
Project Justification
Lift station is needed to account for future wastewater flows and future development.
Spend
Budget Utilization
$825,000 of $825,000 Actual Spent100%
- Construction - $750,000 (90.9%)
- Engineering - $75,000 (9.1%)
| Expenditures | 2028 | 2029 | Total |
|---|---|---|---|
| Construction | 0 | 750,000 | 750,000 |
| Engineering | 75,000 | 0 | 75,000 |
| Total | 75,000 | 750,000 | 825,000 |
| Funding Sources | 2028 | 2029 | Total |
|---|---|---|---|
| San 2 Fund Balance | 75,000 | 750,000 | 825,000 |
| Total | 75,000 | 750,000 | 825,000 |