Grand Chute, Wisconsin
Grand Chute, Wisconsin

Edgewood Dr (Mayflower-Termini) Reclaim/Pave

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$1,152,000

Overview

DepartmentStreets
Project NumberPWSTR-25-026
TypeImprovement
CategoryReclamation
Priority3 Important
StatusActive
Useful Life20 years years
Paser Rating:3
Project Length (mi.):1.25
Budget Items2026Total
Storm - Sanitary District No. 3102,000102,000
Street Overlays/Reclamations920,000920,000
Total1,022,0001,022,000

Project Description

Roadway will be reclaimed and paved. Ditch/culvert improvements will be evaluated and improved where necessary.

Project Justification

Drainage is poor and during larger rain events, the roadway floods. Culvert pipes are undersized.

Spend

PriorExpenditures2026Total
130,000Construction1,022,0001,022,000
Total1,022,0001,022,000
PriorFunding Sources2026Total
130,000General Obligation Debt 2026920,000920,000
San 3 Fund Balance102,000102,000
Total1,022,0001,022,000