Capital Cost

TOTAL PROJECT COST$7,000,000

Overview

DepartmentFire
Project NumberF-26-03
TypeImprovement
CategoryBuildings
Priority1 Critical
StatusActive
Useful Life40 years years
Budget Impact
Fire Impact Fee revenue can be applied towards this project. At thie time of this writing, the balance in the Fire Impact Fee fund is $xx,xxx.
Budget Items2027Total
Building Construction7,000,0007,000,000
Total7,000,0007,000,000

Project Description

New construction of Fire Station Three on Town-owned land at McCarthy Road and Champion Drive.

Project Justification

Construction of this station will provide coverage for the under-served area in the western and northwestern areas of the Town resulting in faster response times. Building on Town-owned land eliminates the cost of land acquisition..

Spend

Expenditures2027Total
Construction7,000,0007,000,000
Total7,000,0007,000,000
Funding Sources2027Total
General Obligation Debt 20267,000,0007,000,000