Capital Cost
Overview
- Department
- Information Technology
- Project Number
- IT-YEARLY-004
- Contact
- IT Director
- Type
- Equipment
- Category
- Equipment Replacement
- Priority
- 2 Very Important
- Status
- Active
- Useful Life
- 10 years
Budget Impact
| Budget Items | 2029 | Total |
|---|---|---|
| Capital Equipment - IT | 75,000 | 75,000 |
| Total | 75,000 | 75,000 |
Project Justification
Upgrading the A/V equipment is essential to facilitating more effective and engaging meetings, ensuring clear communication, and better accessibility for in-person and remote participants. The current equipment becomes outdated and prone to technical issues, which disrupt meetings and hinder productivity. Modernizing the A/V system will support transparency and public participation by providing reliable and high-quality broadcasts.
Project Description
This project entails the purchase and installation/configuration of new A/V equipment for the Town Hall Board Room, along with Fire, Town Hall Conference Rooms, and Town Center Park. A/V equipment of this nature should be upgraded to newer models every 7-10 years to improve audio and video quality, along with being able to support and provide needed features for remote meetings. Up-to-date equipment will allow greater performance in providing town access to meetings with improved quality and less management overhead. AV fixes and upgrades as needed from funding.
Spend
| Prior | Expenditures | 2027 | 2028 | 2029 | 2030 | 2031 | Total | Future |
|---|---|---|---|---|---|---|---|---|
| 20,000 | Other | 20,000 | 40,000 | 40,000 | 20,000 | 20,000 | 140,000 | 130,000 |
| Total | 20,000 | 40,000 | 40,000 | 20,000 | 20,000 | 140,000 |
- IT Infrastructure Replacement Fund - $98,000 (70.0%)
- San 1 Fund Balance - $14,000 (10.0%)
- San 2 Fund Balance - $14,000 (10.0%)
- San 3 Fund Balance - $14,000 (10.0%)
| Prior | Funding Sources | 2027 | 2028 | 2029 | 2030 | 2031 | Total | Future |
|---|---|---|---|---|---|---|---|---|
| 20,000 | IT Infrastructure Replacement Fund | 14,000 | 28,000 | 28,000 | 14,000 | 14,000 | 98,000 | 130,000 |
| San 1 Fund Balance | 2,000 | 4,000 | 4,000 | 2,000 | 2,000 | 14,000 | ||
| San 2 Fund Balance | 2,000 | 4,000 | 4,000 | 2,000 | 2,000 | 14,000 | ||
| San 3 Fund Balance | 2,000 | 4,000 | 4,000 | 2,000 | 2,000 | 14,000 | ||
| Total | 20,000 | 40,000 | 40,000 | 20,000 | 20,000 | 140,000 |