Capital Cost
Overview
- Department
- Streets
- Project Number
- PWSTR-27-004
- Type
- Improvement
- Category
- Reconstruction
- Priority
- 2 Very Important
- Status
- Active
- Useful Life
- 20 years years
- Paser Rating:
- 3
- Project Length (mi.):
- 0.20
- Street Overlays/Reclamations - $644,000 (46.8%)
- Water - Sanitary District No. 1 - $569,000 (41.4%)
- Storm - Sanitary District No. 3 - $60,000 (4.4%)
- Engineering Streets - $52,000 (3.8%)
- Sewer - Sanitary District No. 2 - $50,000 (3.6%)
| Budget Items | 2029 | 2030 | Total |
|---|---|---|---|
| Engineering Streets | 52,000 | 0 | 52,000 |
| Sewer - Sanitary District No. 2 | 0 | 50,000 | 50,000 |
| Storm - Sanitary District No. 3 | 0 | 60,000 | 60,000 |
| Street Overlays/ | 0 | 644,000 | 644,000 |
| Water - Sanitary District No. 1 | 0 | 569,000 | 569,000 |
| Total | 52,000 | 1,323,000 | 1,375,000 |
Project Description
The following roadways will be reconditioned: W Woodstone Dr (N Mason St-N Spruce St), N Spruce St (W Woodstone Dr-W Capitol Dr), W Deerwood Ct (N Spruce St-Termini), W Cherrywood Ct (W Spruce St-Termini), and W Cottonwood Ct (N Spruce St-Termini). Project will include isolated base course repairs, curb & gutter repairs, storm sewer inlet and manhole repairs. Water main hardware and bolts to be replaced on tees and valves. Hydrants and copper services to be replaced. Sanitary manhole to be adjusted to final grade.
Project Justification
Pavement is in poor condition and is beginning to deteriorate. Existing water main was likely installed without stainless steel hardware and bolts, as well as having copper services that have a history of corroding.
Spend
- Construction - $1,323,000 (96.2%)
- Engineering - $52,000 (3.8%)
| Expenditures | 2029 | 2030 | Total |
|---|---|---|---|
| Construction | 0 | 1,323,000 | 1,323,000 |
| Engineering | 52,000 | 0 | 52,000 |
| Total | 52,000 | 1,323,000 | 1,375,000 |
- General Obligation Debt - $696,000 (50.6%)
- San 1 Debt - $569,000 (41.4%)
- San 3 Fund Balance - $60,000 (4.4%)
- SAN 2 Debt - $50,000 (3.6%)
| Funding Sources | 2029 | 2030 | Total |
|---|---|---|---|
| General Obligation Debt | 52,000 | 644,000 | 696,000 |
| San 1 Debt | 0 | 569,000 | 569,000 |
| SAN 2 Debt | 0 | 50,000 | 50,000 |
| San 3 Fund Balance | 0 | 60,000 | 60,000 |
| Total | 52,000 | 1,323,000 | 1,375,000 |