Capital Cost
TOTAL PROJECT COST$930,000
Overview
- Department
- Sanitary District 2 - Sewer
- Project Number
- PWS2-27-002
- Type
- Improvement
- Category
- Wastewater
- Priority
- 3 Important
- Status
- Active
- Useful Life
- 75 years years
- Paser Rating:
- NA
- Project Length (mi.):
- NA
- Sewer - Sanitary District No. 2 - $580,000 (62.4%)
- Streets - Rural Reconstruction - $350,000 (37.6%)
| Budget Items | 2027 | Total |
|---|---|---|
| Sewer - Sanitary District No. 2 | 580,000 | 580,000 |
| Streets - Rural Reconstruction | 350,000 | 350,000 |
| Total | 930,000 | 930,000 |
Project Description
Replacing the existing sanitary sewer along Highview Drive and Lilas Drive. Project will also include reclaiming and paving of the existing roadway.
Project Justification
Sanitary sewer televising completed in 2025 identified significant deficiences in the existing sanitary sewer pipe located along Highview Drive and Lilas Drive. Roadway surface is deteriorating and is past pavement maintenance/preservation methods.
Spend
Budget Utilization
$930,000 of $930,000 Actual Spent100%
| Expenditures | 2027 | Total |
|---|---|---|
| Construction | 930,000 | 930,000 |
| Total | 930,000 | 930,000 |
- San 2 Fund Balance - $580,000 (62.4%)
- General Obligation Debt - $350,000 (37.6%)
| Funding Sources | 2027 | Total |
|---|---|---|
| General Obligation Debt | 350,000 | 350,000 |
| San 2 Fund Balance | 580,000 | 580,000 |
| Total | 930,000 | 930,000 |