Capital Cost

TOTAL PROJECT COST$160,000

Overview

Department
Information Technology
Project Number
IT-28-001
Contact
IT Director
Type
Equipment
Category
Equipment Replacement
Priority
1 Critical
Status
Active
Useful Life
6 years

Budget Impact

2028 budget impact of this project will be $160,000 as phase 1 to replace 2 servers. 

Budget Items
Budget Items2028Total
Capital Equipment - IT160,000160,000
Total160,000160,000

Project Description

This is a multi-year project to update our server structure to be under support and software updates.  Two servers will be replaced in 2028 and 1 server will be replaced in the year 2029.

Project Justification

Servers are critical to our environment as the main source of our communication software.  These replacements will enable us to continue secure and reliable Town operations.  At time of replacement the current servers will be 1 year past end of support.

Spend

Expenditures
Expenditures2028Total
No Name160,000160,000
Total160,000160,000
  • General Obligation Debt - $112,000 (70.0%)
  • San 1 Debt - $16,000 (10.0%)
  • SAN 2 Debt - $16,000 (10.0%)
  • San 3 Fund Balance - $16,000 (10.0%)
Funding Sources
Funding Sources2028Total
General Obligation Debt112,000112,000
San 1 Debt16,00016,000
SAN 2 Debt16,00016,000
San 3 Fund Balance16,00016,000
Total160,000160,000