Do you have thoughts or questions about INTERSECTION SIGNAL CONTROL HARDWARE? Your feedback goes directly to Grand Chute, Wisconsin staff — it is never posted on this website.
Capital Cost
Overview
- Department
- Street Equipment
- Project Number
- PWSTR-27-402
- Contact
- Public Works Director
- Type
- Equipment
- Category
- Equipment: Miscellaneous
- Priority
- 1 Critical
- Status
- Active
- Useful Life
- 7 years
Budget Impact
Impact to 2027 budget will be a cost of $65,000 over the year to update signal control capabilities at 10 intersections.
| Budget Items | 2027 | Total |
|---|---|---|
| Street Other | 85,000 | 85,000 |
| Total | 85,000 | 85,000 |
Project Description
Purchase necessary hardware for 10 intersections to allow for signal control maintained by City of Appleton.
Equipment includes: 10 each of the following, Cradlepoints, power converters, Cisco Meraki access points, Cisco power supplies, network switch.
Project Justification
The City of Appleton will no longer go on site to update signal light controls at Grand Chute intersections. 10 outdated intersections that the City maintains must be converted to a remote solution by end of 2027.
Intersections affected are:
Bluemound/Spencer Casaloma/Federated Casaloma/Michaels Sams's Club / Westhill Nicolet / Spencer
Casaloma/Greenville (CTH GV) Casaloma/Integrity Way Lyndale (CTH A) / Spencer Mall / Metro Westhill / Woodman
Spend
| Expenditures | 2027 | Total |
|---|---|---|
| Equipment/ | 85,000 | 85,000 |
| Total | 85,000 | 85,000 |
| Funding Sources | 2027 | Total |
|---|---|---|
| General Obligation Debt | 85,000 | 85,000 |
| Total | 85,000 | 85,000 |