Grand Chute, Wisconsin
Grand Chute, Wisconsin

Lions Park Playground/PIP

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$295,000

Overview

DepartmentParks and Recreation
Project NumberPR-26-003
TypeUnassigned
CategoryPark Improvements
Priority3 Important
StatusActive
Useful Life20 years years
Budget Items2030Total
Capital Equipment - Parks295,000295,000
Total295,000295,000

Project Description

Reconstruction of the existing playground, with Pour-In-Place (PIP) Surface and a perimeter walk around the site.

Project Justification

As the existing playground ages, plastic pieces start to fail with age and replacement parts become unavailable. Poured-in-place (PIP) surfacing extends the usable season for playground equipment, and provides an extremely safe surface for all playground users.  

Spend

Expenditures2030Total
Construction295,000295,000
Total295,000295,000
Funding Sources2030Total
General Obligation Debt 2030295,000295,000
Total295,000295,000