Capital Cost
TOTAL PROJECT COST$240,000
Overview
- Department
- Street Equipment
- Project Number
- PWSTR-26-403
- Type
- Unassigned
- Category
- Vehicles
- Priority
- 2 Very Important
- Status
- Active
- Useful Life
- 10 years years
- Capital Equipment - San 3 VEH - $120,000 (50.0%)
- Capital Equipment - Streets - $120,000 (50.0%)
| Budget Items | 2027 | Total |
|---|---|---|
| Capital Equipment - San 3 VEH | 120,000 | 120,000 |
| Capital Equipment - Streets | 120,000 | 120,000 |
| Total | 240,000 | 240,000 |
Project Description
The vehicle will be used by the Streets department for hauling materials and tools to and from the jobsite for concrete work. It will have the ability to unload pallets of material, forms, and any larger sized items or equipment with the crane.
Project Justification
New vehicle for streets department.
Spend
Budget Utilization
$240,000 of $240,000 Actual Spent100%
| Expenditures | 2027 | Total |
|---|---|---|
| Equipment/ | 240,000 | 240,000 |
| Total | 240,000 | 240,000 |
- General Obligation Debt - $120,000 (50.0%)
- San 3 Fund Balance - $120,000 (50.0%)
| Funding Sources | 2027 | Total |
|---|---|---|
| General Obligation Debt | 120,000 | 120,000 |
| San 3 Fund Balance | 120,000 | 120,000 |
| Total | 240,000 | 240,000 |