Capital Cost
TOTAL PROJECT COST$70,000
Overview
DepartmentParks and Recreation
Project NumberPR-26-007
TypeImprovement
CategoryPark Improvements
Priority3 Important
StatusActive
Useful Life15 years
| Budget Items | 2027 | Total | ||
|---|---|---|---|---|
| Park Improvement | 70,000 | 70,000 | ||
| Total | 70,000 | 70,000 |
Project Description
Installation of batting cage structures near ballfield.
Project Justification
The current site of the street hockey rink provides an excellent location for ballfield themed amenities. Local baseball organizations, who use the current facility on a yearly basis, have shown support for these practice areas.
Spend
| Expenditures | 2027 | Total | ||
|---|---|---|---|---|
| Construction | 70,000 | 70,000 | ||
| Total | 70,000 | 70,000 |
| Funding Sources | 2027 | Total | ||
|---|---|---|---|---|
| General Obligation Debt 2028 | 70,000 | 70,000 | ||
| Total | 70,000 | 70,000 |