Capital Cost
TOTAL PROJECT COST$45,960,554
Overview
- Department
- Administration
- Project Number
- ADM-26-05
- Contact
- Town Administrator
- Type
- Improvement
- Category
- Facility Improvement
- Priority
- 1 Critical
- Status
- Active
- Useful Life
- 20 years
Project Justification
Current space at Town Hall is not large enough to fit all staff. Police and Municipal Court will be moved to the new Public Safety building and the current Town Hall will be reconfigured to fit current staff and allow for future growth.
Project Description
Build a public safety building and remodel town hall
Spend
- Construction - $40,960,554 (89.1%)
- Engineering - $5,000,000 (10.9%)
| Expenditures | 2027 | 2028 | 2029 | Total |
|---|---|---|---|---|
| Construction | 0 | 20,480,277 | 20,480,277 | 40,960,554 |
| Engineering | 5,000,000 | 0 | 0 | 5,000,000 |
| Total | 5,000,000 | 20,480,277 | 20,480,277 | 45,960,554 |
- General Obligation Debt - $45,210,554 (98.4%)
- Fire Impact Fund - $750,000 (1.6%)
| Funding Sources | 2027 | 2028 | 2029 | Total |
|---|---|---|---|---|
| Fire Impact Fund | 750,000 | 0 | 0 | 750,000 |
| General Obligation Debt | 4,250,000 | 20,480,277 | 20,480,277 | 45,210,554 |
| Total | 5,000,000 | 20,480,277 | 20,480,277 | 45,960,554 |