Grand Chute, Wisconsin
Grand Chute, Wisconsin

Resurface Staff Parking Lot & Yard

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$709,400

Overview

DepartmentAdministration
Project NumberADM-20-01
TypeImprovement
CategoryReclamation
Priority3 Important
StatusActive
Useful Life20 years years
Paser Rating:NA
Project Length (mi.):NA
Budget Items20292030Total
Engineering Streets35,000035,000
Street Overlays/Reclamations0674,400674,400
Total35,000674,400709,400

Project Description

The parking lot and yard will be pulverized and re-paved. Striping will be upated to meet ADA requirements and improve circulation. Storm sewer repairs and improvements will be made.

Project Justification

The parking lot and yard is cracking and is in need of reconstruction. Storm sewer pipes are raised from frost.

Spend

Expenditures20292030Total
Construction0674,400674,400
Engineering35,000035,000
Total35,000674,400709,400
Funding Sources20292030Total
General Obligation Debt 20300674,400709,400