Capital Cost
TOTAL PROJECT COST$709,400
Overview
DepartmentAdministration
Project NumberADM-20-01
TypeImprovement
CategoryReclamation
Priority3 Important
StatusActive
Useful Life20 years years
Paser Rating:NA
Project Length (mi.):NA
| Budget Items | 2029 | 2030 | Total | ||
|---|---|---|---|---|---|
| Engineering Streets | 35,000 | 0 | 35,000 | ||
| Street Overlays/Reclamations | 0 | 674,400 | 674,400 | ||
| Total | 35,000 | 674,400 | 709,400 |
Project Description
The parking lot and yard will be pulverized and re-paved. Striping will be upated to meet ADA requirements and improve circulation. Storm sewer repairs and improvements will be made.
Project Justification
The parking lot and yard is cracking and is in need of reconstruction. Storm sewer pipes are raised from frost.
Spend
| Expenditures | 2029 | 2030 | Total | ||
|---|---|---|---|---|---|
| Construction | 0 | 674,400 | 674,400 | ||
| Engineering | 35,000 | 0 | 35,000 | ||
| Total | 35,000 | 674,400 | 709,400 |
| Funding Sources | 2029 | 2030 | Total | ||
|---|---|---|---|---|---|
| General Obligation Debt 2030 | 0 | 674,400 | 709,400 | ||
| Total | 0 | 674,400 | 709,400 |