S Nicolet Rd Urban Recondition (Pine-Van Dyke)

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$759,000

Overview

DepartmentStreets
Project NumberPWSTR-26-004
TypeImprovement
CategoryReconstruction
Priority2 Very Important
StatusActive
Useful Life20 years years
Paser Rating:3
Project Length (mi.):0.20
Budget Items20292030Total
Engineering Streets54,000054,000
Sewer - Sanitary District No. 2030,00030,000
Storm - Sanitary District No. 3066,00066,000
Street Overlays/Reclamations0609,000609,000
Total54,000705,000759,000

Project Description

S Nicolet Rd will be reconditioned from Pine St to Van Dyke Rd.  Project will include base course repairs, curb & gutter repairs, storm sewer inlet and manhole repairs, and sanitary sewer maintenance.

Project Justification

Pavement is in poor condition and beginning to deteriorate.

Spend

Expenditures20292030Total
Construction0705,000705,000
Engineering54,000054,000
Total54,000705,000759,000
Funding Sources20292030Total
General Obligation Debt 20300609,000663,000
San 2 Fund Balance030,00030,000
San 3 Fund Balance066,00066,000
Total0705,000759,000