Grand Chute, Wisconsin
Grand Chute, Wisconsin

STH 47/Ridgeview Dr Signalization

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$65,000

Overview

DepartmentStreets
Project NumberPWSTR-25-010
TypeImprovement
CategoryFacility Improvement
Priority2 Very Important
StatusActive
Useful Life20 years
Budget Items2026Total
Capital Equipment - Streets41,00041,000
Total41,00041,000

Project Description

Design and construction of traffic signals at the intersection of STH 47 and Ridgeview Dr.  The project is contingent on successfully obtaining Signals and ITS Standalone Program (SISP) grant funding.

Project Justification

In response to traffic complaints, the City of Appleton conducted a traffic operations study in 2023 of the STH 47/Ridgeview Dr intersection.  The study revealed that traffic volumes are approaching warrant thresholds for signalization and crash volumes already meet the warrant.  As part of the I-41 construction project, the Wisconsin Department of Transportation will implement temporary traffic signals at this intersection in April 2025.  This temporary measure aims to mitigate the expected increase of traffic along STH 47 as a result of the closure of the I-41/Ballard Rd interchange.  The temporary traffic signal will establish public expectations for permanent signalization.  This temporary signal is also expected to induce traffic on Ridgeview Dr and result in additional signal warrants to be met.

Spend

PriorExpenditures2026Total
24,000Construction41,00041,000
Total41,00041,000
PriorFunding Sources2026Total
24,000General Obligation Debt 202641,00041,000
Total41,00041,000