Sunnyview Rd Bridge Replacement

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$674,270

Overview

DepartmentSanitary District 3 - Storm
Project NumberPWS3-27-001
TypeImprovement
CategoryBridges
Priority2 Very Important
StatusActive
Useful Life75 years years
Paser Rating:NA
Project Length (mi.):NA
Budget Impact

Grant application has been submitted and approved which would cover 100% engineering and participating construction items through the Wisconsin Department of Transportation's Local Bridge Program.

Budget Items20262028Total
Storm - Sanitary District No. 30515,000649,270
Water - Sanitary District No. 1025,00025,000
Total0540,000674,270

Project Description

Replace existing bridge structure (B-44-491) with a single span bridge structure.

Project Justification

The existing structure is a triple steel culvert run with two of those culverts having severe corrosion along the waterline. As a result, the current bridge sufficiency rating based on the 2022 inspection report is 42.9. The center culvert has severe corrosion which has resulted in failure along the waterline; the east culvert has severe corrosion along the waterline, which has resulted in a partial failure of the north upstream end. Some settlement of the beam guard above the failed culvert section has occurred. One sanitary manhole on the west approach will require adjustment based on final pavement grades. The depth of the existing water main is unknown beneath the current structure; it will be assumed that beneath the new structure, the existing water main will need to be lowered to account for any overexcavation, or new structural elements.

Spend

Expenditures20262028Total
Construction0540,000540,000
Engineering124,2700124,270
Land/ROW Acquisition10,000010,000
Total134,270540,000674,270
Funding Sources20262028Total
Grants Other0487,131611,401
San 1 Debt025,00025,000
San 3 Fund Balance10,000037,869
Total10,000512,131674,270