Grand Chute, Wisconsin
Grand Chute, Wisconsin

Timmers Ln/Kools Ct Reclaim/Pave

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$894,000

Overview

DepartmentStreets
Project NumberPWSTR-25-012
TypeImprovement
CategoryReclamation
Priority3 Important
StatusActive
Useful Life20 years
Budget Items20262027Total
Engineering Streets52,400052,400
Sewer - Sanitary District No. 2017,10017,100
Storm - Sanitary District No. 3065,00065,000
Street Overlays/Reclamations0461,600461,600
Water - Sanitary District No. 123,8000297,900
Total76,200543,700894,000

Project Description

The following roadways will be reclaimed and paved: S Timmers Ln (W Spencer St-Termini) and S Kools Ct (W Spencer St-Termini) . Isolated ditch improvements will be evaluated and improved where necessary. Water main to be replaced on Kools Ct.  Water main hardware to be replaced on Timmers Ln if in poor condition. Sanitary manhole to be adjusted to final grade. Culverts will be reviewed and replaced if needed.

Project Justification

Roadway surface is deteriorating and is past pavement maintenance/preservation methods. Project will include replacement of bolts for water valves and hydrants.  Corrosive soils have deteriorated the existing ductile iron water main. The Town desires to reduce water loss associated with leaks and water main breaks. Both leaks and breaks contribute to water loss in the Town.

Spend

Expenditures20262027Total
Construction0817,800817,800
Engineering76,200076,200
Total76,200817,800894,000
Funding Sources20262027Total
General Obligation Debt 202652,400052,400
General Obligation Debt 20280461,600461,600
San 1 Debt23,8000297,900
San 2 Fund Balance017,10017,100
San 3 Fund Balance065,00065,000
Total76,200543,700894,000