Capital Cost
TOTAL PROJECT COST$900,000
Overview
DepartmentStreets
Project NumberPWSTR-25-014
TypeImprovement
CategoryReconstruction
Priority2 Very Important
StatusActive
Useful Life25 years
| Budget Items | 2027 | 2028 | Total | ||
|---|---|---|---|---|---|
| Engineering Streets | 65,000 | 0 | 65,000 | ||
| Street Other | 0 | 835,000 | 835,000 | ||
| Total | 65,000 | 835,000 | 900,000 |
Project Description
The roadway improvements include reconditioning of the existing pavement in Grand Chute Blvd from CTH A to the Fire Station as well as miscellaneous roadway enhancements including new sidewalk, terrace/street trees, traffic calming measures, and entrance features.
Project Justification
Tax Increment Finance funds are proposed to facilitate roadway improvements and enhancements along the Town Center District corridor.
Spend
| Expenditures | 2027 | 2028 | Total | ||
|---|---|---|---|---|---|
| Construction | 0 | 835,000 | 835,000 | ||
| Engineering | 65,000 | 0 | 65,000 | ||
| Total | 65,000 | 835,000 | 900,000 |
| Funding Sources | 2027 | 2028 | Total | ||
|---|---|---|---|---|---|
| TID #2 - Debt | 65,000 | 0 | 900,000 | ||
| Total | 65,000 | 0 | 900,000 |