W Brewster St (Bluemound-Lynndale Frontage Rd)

Share your feedback

Do you have thoughts or questions about W Brewster St (Bluemound-Lynndale Frontage Rd)? Your feedback goes directly to Grand Chute, Wisconsin staff — it is never posted on this website.

Capital Cost

TOTAL PROJECT COST$3,841,000

Overview

Department
Streets
Project Number
PWSTR-25-009
Type
Improvement
Category
Reconstruction
Priority
2 Very Important
Status
Active
Useful Life
20 years years
Paser Rating:
6
Project Length (mi.):
0.25
  • Street Overlays/Reclamations - $1,861,000 (48.5%)
  • Storm - Sanitary District No. 3 - $704,000 (18.3%)
  • Water - Sanitary District No. 1 - $614,000 (16.0%)
  • Sewer - Sanitary District No. 2 - $498,000 (13.0%)
  • Engineering Streets - $164,000 (4.3%)
Budget Items
Budget Items20292031Total
Engineering Streets164,0000164,000
Sewer - Sanitary District No. 20498,000498,000
Storm - Sanitary District No. 310,000694,000704,000
Street Overlays/Reclamations01,861,0001,861,000
Water - Sanitary District No. 10614,000614,000
Total174,0003,667,0003,841,000

Project Justification

Roadway is in poor condition. Drainage is poor. No bike/ped facilities are present.

Project Description

W Brewster St (Bluemound-Lilas) will have a full depth mill and overlay of the existing roadway pavement. It will include constructing a 5' sidewalk south of roadway between Popp Ln and Lilas Dr to provide connectivity to existing sidewalk to the west.  Curb & gutter will be spot repaired.  Water main will have hardware replaced and hydrants/valves evaluated.  Sanitary sewer will be reviewed and replaced as needed.

W Brewster St (Lilas-Lynndale Frontage Rd) is planned to be urbanized with curb and gutter and storm sewer. Construct 5' sidewalk south of roadway to provide connectivity to existing pedestrian facilities.  Sanitary sewer will be reviewed and replaced as needed. Water main will have hardware replaced and hydrants/valves evaluated.

N Hine St (Brewster-Randall), N Rexford St (Brewster-Randall), N Rynders St (Brewster-Randall), E Frontage Rd (Brewster-Randall), and W Randall St (Hines-E Frontage) will be reclaimed and paved as part of this project.

Spend

Budget Utilization
$3,841,000 of $3,841,000 Actual Spent100%
  • Construction - $3,667,000 (95.5%)
  • Engineering - $174,000 (4.5%)
Expenditures
Expenditures20292031Total
Construction03,667,0003,667,000
Engineering174,0000174,000
Total174,0003,667,0003,841,000
  • General Obligation Debt - $2,025,000 (52.7%)
  • San 3 Fund Balance - $704,000 (18.3%)
  • San 1 Debt - $614,000 (16.0%)
  • SAN 2 Debt - $498,000 (13.0%)
Funding Sources
Funding Sources20292031Total
General Obligation Debt164,0001,861,0002,025,000
San 1 Debt0614,000614,000
SAN 2 Debt0498,000498,000
San 3 Fund Balance10,000694,000704,000
Total174,0003,667,0003,841,000