Grand Chute, WisconsinGrand Chute, Wisconsin

W Fourth St (Bluemound-Lynndale)

Share your feedback

Do you have thoughts or questions about W Fourth St (Bluemound-Lynndale)? Your feedback goes directly to Grand Chute, Wisconsin staff — it is never posted on this website.

Capital Cost

TOTAL PROJECT COST$3,320,000

Overview

Department
Streets
Project Number
PWSTR-28-001
Type
Improvement
Category
Reconstruction
Priority
2 Very Important
Status
Active
Useful Life
25 years
Paser Rating:
3
Project Length (mi.):
0.50
  • Street Urbanization - $1,880,000 (56.6%)
  • Storm - Sanitary District No. 3 - $1,125,000 (33.9%)
  • Engineering Streets - $155,000 (4.7%)
  • Water - Sanitary District No. 1 - $122,000 (3.7%)
  • Sewer - Sanitary District No. 2 - $38,000 (1.1%)
Budget Items
Budget Items20282030Total
Engineering Streets155,0000155,000
Sewer - Sanitary District No. 2038,00038,000
Storm - Sanitary District No. 3280,000845,0001,125,000
Street Urbanization01,880,0001,880,000
Water - Sanitary District No. 10122,000122,000
Total435,0002,885,0003,320,000

Project Description

Urbanization of roadway with sidewalk. Anticipated sewer and water main relay, but will be evaluated prior to design.

Project Justification

Roadway is in poor condition. Drainage is substandard within the roadside ditches.

Spend

Budget Utilization
$3,320,000 of $3,320,000 Actual Spent100%
  • Construction - $2,885,000 (86.9%)
  • Land/ROW Acquisition - $250,000 (7.5%)
  • Engineering - $185,000 (5.6%)
Expenditures
Expenditures20282030Total
Construction02,885,0002,885,000
Engineering185,0000185,000
Land/ROW Acquisition250,0000250,000
Total435,0002,885,0003,320,000
  • General Obligation Debt - $2,035,000 (61.3%)
  • San 3 Fund Balance - $1,125,000 (33.9%)
  • San 1 Debt - $122,000 (3.7%)
  • San 2 Fund Balance - $38,000 (1.1%)
Funding Sources
Funding Sources20282030Total
General Obligation Debt155,0001,880,0002,035,000
San 1 Debt0122,000122,000
San 2 Fund Balance038,00038,000
San 3 Fund Balance280,000845,0001,125,000
Total435,0002,885,0003,320,000