Capital Cost

TOTAL PROJECT COST$1,558,478

Overview

Department
Sanitary District 1 - Water
Project Number
W2708
Contact
Deputy Director of Public Works
Type
Improvement
Category
Equipment Replacement
Priority
2 Very Important
Status
Active
Useful Life
10 years

Project Description

Water meter replacement program to convert to full Kamstrup complement of meters.  This is the last major purchase to finish the conversion by the end of 2027.

Project Justification

Sanitary District #1 (Water) will take delivery of the meters after January 1st 2027. By combining the final two years purchases of the conversion, we will save on annual increases in meter pricing, and we would be fully integrated with Kamstrup meters and software by the end of 2027.

Spend

Expenditures
Expenditures2027Total
Equipment/Vehicles1,558,4781,558,478
Total1,558,4781,558,478
  • General Obligation Debt - $1,000,000 (64.2%)
  • San 1 Fund Balance - $558,478 (35.8%)
Funding Sources
Funding Sources2027Total
General Obligation Debt1,000,0001,000,000
San 1 Fund Balance558,478558,478
Total1,558,4781,558,478