Grand Chute, Wisconsin
Grand Chute, Wisconsin

Wisconsin Ave Relay/Rehab (Bluemound-Badger)

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$3,071,000

Overview

DepartmentSanitary District 1 - Water
Project NumberPWS1-25-001
TypeImprovement
CategoryWater
Priority2 Very Important
StatusActive
Useful Life75 years
Budget Items20262027Total
Sewer - Sanitary District No. 246,0000721,000
Water - Sanitary District No. 1150,00002,350,000
Total196,00003,071,000

Project Description

Continuation of the Wisconsin Ave Utility replacement project.  This section is located along the south side of Wisconsin Ave between Bluemound Dr and Badger Ave.

GCSD 1 - Replace the existing water main, hydrants, and water services.

GCSD 2 - Replace or rehabilitate the existing sanitary sewer and lateral connections.

Project Justification

Corrosive soils have deteriorated the existing ductile iron water main, which was installed in approximately year 1975. The Town desires to reduce water loss associated with leaks and water main breaks. Both leaks and breaks contribute to water loss in the Town.

Based on televising, the existing sanitary sewers have leaks and other deformities. The existing sanitary sewers were installed in approximately year 1967.

Spend

Expenditures20262027Total
Construction02,875,0002,875,000
Engineering196,0000196,000
Total196,0002,875,0003,071,000
Funding Sources20262027Total
San 1 Debt150,00002,350,000
San 2 Fund Balance46,0000721,000
Total196,00003,071,000