Wisconsin Ave Sidewalk (Westhill-Bluemound)

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$1,066,515.18

Overview

DepartmentStreets
Project NumberPWSTR-24-026
TypeImprovement
CategoryUrbanization
Priority2 Very Important
StatusActive
Useful Life20 years years
Paser Rating:NA
Project Length (mi.):0.22
Budget Impact

WisDOT approved a federal award limit of $853,212.14 through the Transportation Alternative Progam (TAP) for this project.

Budget Items20262028Total
Engineering Streets91,922.19091,922.19
Sidewalk Construction0929,592.99929,592.99
Storm - Sanitary District No. 3045,00045,000
Total91,922.19974,592.991,066,515.18

Project Description

The sidewalk will be located on the north side of STH 96. The west end of the project will start at N Westhill Boulevard and will terminate at N. Bluemound Drive, which spans approximately 0.22 miles.

Project Justification

This section will be the final sidewalk connection on the north side of STH 96 from N. Casaloma Drive to N. Badger Ave. The project shows a clear and evident need based on both safety concerns and overall network connectivity. A Fox Valley transit route runs along the project limits, and the addition of the sidewalk would allow for safer transit user access to multiple stops and a transit shelter 400 feet from the project termini.

Spend

Expenditures20262028Total
Construction0974,592.99974,592.99
Engineering91,922.19091,922.19
Total91,922.19974,592.991,066,515.18
Funding Sources20262028Total
General Obligation Debt 202618,384.44018,384.44
General Obligation Debt 20280149,918.6149,918.6
Grants Other0779,674.39853,212.14
San 3 Fund Balance045,00045,000
Total18,384.44974,592.991,066,515.18